How to make a floor tie

How to make a floor tie

Before reducing the floor covering, it is necessary to level the base qualitatively. Laminate is particularly demanding in this regard, since the drops of more than 2-3 millimeters quickly destroy the locking plate of the plates. Today you will learn about how to independently organize a cement-sand tie in the room.



1
How to make a floor screed - surface grain

Work begins with the priming of the surface. Often, builders skip the preparatory part, considering it optional. However, the composition allows you to completely get rid of dust on the floor, which significantly improves the adhesion of materials. Liquid impregnate floor with a wide painting roller. In the process of processing, it is desirable not to leave poorly intermitted areas.



2
How to make a floor tie - guide lighthouses

Next, the guide lighthouses are exhibited. This is the most responsible stage, since the quality of the foundation depends on the correctness of their installation. To set lighthouses, you need to purchase them in the required quantity, after which it is fixed on the floor cement or gypsum mixture. Each lighthouse is checked by a construction level to observe the unified plane.
In the standard room room, there are enough two rows of lighthouses. They are exhibited at some distance from each other with the calculation under the two-meter plaster rule. It should slide on them as rails.

3
How to make a floor screed - tie height

The height of the screed depends on the available base drops. But in any case it is desirable that it is at least three centimeters. Otherwise, the need for it disappears, since it is more profitable to use a self-leveling liquid mixture with differentials up to two centimeters.

4
How to make a floor screed - soloing the solution under beacons

After installing the beacons, it will take some time to frozen the solution. Typically, to remove the plane with a solution start the day after they are installed, since poorly fixed guides can progress when pressed by the rule.

5
How to make a floor tie - floor fill

The final stage consists in the pouring of the floor with a mixture. This work is most convenient to perform with a partner. One person kneads the solution in the tank with a perforator equipped with a spiral-like nozzle. The second - pulls it with a plaster rule for beacons.
Pouring starts from the far corner of the room and gradually move to the exit. Thus, it is possible to align the floor with a tie within one day. The need to later return to unfinished areas disappears.

We hope our instruction was useful for you. Now you know how to make a tie from cement and sand with your own hands. As a result, the floor covering on the prepared base will serve longer than the usual one.