If information about the penalty measures are made to your contract, then in the context of violation of obligations, the debtor pays you a penalty - the monetary compensation of damage. It is important to be able to make compensation correctly.
A penalty or penalty is paid as a penalty. The nature of the violation determines the type of penalty. The fine is most often punishable to non-compliance with the quality of execution, and penny is the delay in the timing of execution. The amount of the fine is unchanged and paid once. The value of the penalty is the variable value, and its calculation is due to several points.- total debt size by agreement;
- percentage of penalties;
- the number of days of delay.
- aggregate debt under the contract - 100,000;
- percentage of penalties for each day of delay - 1%;
- delay in the implementation of requirements - 10 days.
We need to calculate the amount of compensation for the real 10 days of execution delay. The calculation formula will look as follows: total debt at 100,000 is multiplied by 1% penalty and multiplied by 10 days of delay. The total amount of 10,000 and there is the amount of recovery to which you can qualify for 10 overdue days.

Remember that only writing certified information on penalties gives you the right in case of failure to expect a penalty.